Getting a Domestic Connection
Thank you for associating with Kerala’s largest Public Sector Undertaking and giving us an opportunity to serve you. You are requested to go through the instructions carefully before filling up the application form.
Click here for Online
Registration
- The following two documents are mandatory for all applicants for new service connection
- Proof of Identity of the Applicant -Applicants shall furnish any of the documents listed below as proof of Identity.
(Electoral Identity Card/Indian Passport/Driving Licence/Ration Card/Photo Identity Card issued by any Government Agency/PAN Card/AADHAR Card/Photo Identify Certificate from Village Panchayat or Municipality or Municipal Corporation). -
Proof of ownership or occupancy of the premises – Applicants shall furnish any of the documents listed below as proof of ownership.
(Ownership certificate of the building issued by Municipal Corporation or Panchayat / Ownership or Possession certificate of the land issued by competent Revenue authority / Copy of title deed duly attested by a Gazetted Officer or KSEB Ltd officer /Copy of the Land Tax payment receipt issued by Revenue authorities issued
within 1 year/ Occupancy certificate from Municipal Corporation or Panchayat ).
An applicant who is not an owner but an occupier of the premises/tenant, shall furnish a no objection certificate from the owner of the premises along with any of the documents listed above. -
Any one of the following documents (issued in the address mentioned in the application) can also be submitted as proof of ownership in place of the above documents.
-
Residential Certificate issued by local body/Electoral identity card / Indian
passport / AADHAR card / Ration card/ Photo identity card issued by any Government agency, most recent
water or telephone or gas connection bill issued by Government company or
agency / NREGP (Desiya Grameena Thozhil Urappu Padhathi) card
-
Approved plan / building permit issued by local body for Construction sites
-
- Proof of Identity of the Applicant -Applicants shall furnish any of the documents listed below as proof of Identity.
- Charges payable for New Connection
- All Low Tension(LT) applicants can submit online application for new service connection by payment of Application Fees of Rs 50 /-
-
LT Domestic category applicants having connected load upto and including 20 kW
who require only Weather Proof service less than or equal to 35 m (i.e. not requiring construction of OH line including phase addition, installation of support poles, pole insertion etc) for
effecting service connection can opt for Package Connection (Service connection before field verification). Such applicants can remit online all the requisite fees for new service connection including Application fees, Security Deposit and entire expenditure for Service connection. For such applicants
connection shall be arranged (possibly in two working days time) if there is no pending service connection application in that category. The inspecting personnel accompanying the team effecting service connection will verify the details. However if any additional information, consent or sanction is required for effecting the service, the service connection will not be effected until necessary orders are obtained from the competent authority. The applicant has to agree to remit additional amounts if any, on demand, after inspection. -
For applicants where overhead line extension or installation of poles (support, insertion etc) is required for effecting service connection, the cost can be ascertained only after field inspection. Such Applicants can submit their application online and pay the required Application Fee. The cost (Estimated cost for Service connection + Security Deposit) thus ascertained during field inspection will be intimated to the applicant through e-mail and sms after inspection and the applicant need to remit the amount subsequently.
- Options available:
-
If applicant desires a particular date of Inspection he/she can specify the date. If field verification is carried out on the specified date, the inspecting officer shall demand additional fee for the same along with the Estimate Cost for Service connection. -
If the applicant opts to procure the meter, the tested meter along with the original test certificate has to be produced at site(premise) prior to effecting of service connection. Such applicants are eligible for exemption of monthly meter rent.
-
- Form Submission:
-
After submitting the application online, the applicant shall take a print out of the system generated form, and hand over to the KSEB Ltd personnel, after affixing signature & photograph along with other required documents, during site inspection / while effecting service connection. Please produce the original document for verification. - KSEBL will be forced to terminate the service connection and dismantle service connection without prior notice, if it is proved at any stage that the service connection was availed by hiding facts/fabricating false consents or orders. Any amount remitted by such consumer is liable to be forfeited. The consumer will be liable for any loss sustained by KSEBL on this account.
-
Click here
to continue
Getting a Non-Domestic Connection
Thank you for associating with Kerala’s largest Public Sector Undertaking and giving us an opportunity to serve you. You are requested to go through the instructions carefully before filling up the application form.
Click here for Online
Registration
- The following 2 documents are mandatory for all applicants for new service connection
- Proof of Identity of the Applicant -Applicants shall furnish any of the documents listed below as proof of Identity.
(Electoral Identity Card/Indian Passport/Driving Licence/Ration Card/Photo Identity Card issued by any Government Agency/PAN Card/AADHAR Card/Photo Identify Certificate from Village Panchayat or Municipality or Municipal Corporation). -
Proof of ownership or occupancy of the premises – Applicants shall furnish any of the documents listed below as proof of ownership.
(Ownership certificate of the building issued by Municipal Corporation or Municipality or Panchayat or Township / Ownership or Possession certificate of the land issued by competent Revenue authority / Certified copy of title deed or lease agreement / letter of authorisation from the Punja/Kole Special Officer in the case of agricultural connections for dewatering/ letter of allotment in the case of industrial estates or industrial parks or Special Economic Zones).
An applicant who is not an owner but an occupier of the premises/tenant, shall furnish a no objection certificate from the owner of the premises along with any of the documents listed above.
- Proof of Identity of the Applicant -Applicants shall furnish any of the documents listed below as proof of Identity.
- For the below mentioned category of applicants the following documents shall also be submitted along with the application form.
- Agricultural connection –
In the case of agricultural connections in Punja or Kole land, letter of
authorisation from the Punja / Kole special officer is required. If water is to be
pumped from state owned rivers, canals, ponds, wells etc, NOC from
authorised officer also is required - Non-domestic Kiosks, telecom tower and temporary structure – NOC for kiosk or temporary structure from the Municipal corporation or Municipality or grama Panchayat or land development authority or land owning agency.
- If Service Connection is required for juridical persons, e.g. company (proprietary or partnership), trust, educational institution, Government department or similar institution, a letter of authorisation/resolution will be required along with proof of identity.
- Letter of allotment from competent authority is required for Service
Connections in industrial estates or industrial parks or Special Economic
Zones (proof of ownership is not required in this case)
- Agricultural connection –
- Charges payable for New Connection
- All Low Tension(LT) applicants can submit online application for new service connection by payment of Application Fees of Rs 50 /-
-
LT Non-Domestic category applicants having connected load upto and including 10 kW
who require only Weather Proof service less than or equal to 35 m (i.e. not requiring construction of OH line including phase addition, installation of support poles, pole insertion etc) for
effecting service connection can opt for Package Connection (Service connection before field verification). Such applicants can remit online all the requisite fees for new service connection including Application fees, Security Deposit and entire expenditure for Service connection. For such applicants
connection shall be arranged (possibly in two working days time) if there is no pending service connection application in that category. The inspecting personnel accompanying the team effecting service connection will verify the details. However if any additional information, consent or sanction is required for effecting the service, the service connection will not be effected until necessary orders are obtained from the competent authority. The applicant has to agree to remit additional amounts if any, on demand, after inspection. -
For applicants where overhead line extension or installation of poles (support, insertion etc) is required for effecting service connection, the cost can be ascertained only after field inspection. Such Applicants can submit their application online and pay the required Application Fee. The cost (Estimated cost for Service connection + Security Deposit) thus ascertained during field inspection will be intimated to the applicant through e-mail and sms after inspection and the applicant need to remit the amount subsequently.
- Options available:
-
If applicant desires a particular date of Inspection he/she can specify the date. If field verification is carried out on the specified date, the inspecting officer shall demand additional fee for the same along with the Estimate Cost for Service connection. -
If the applicant opts to procure the meter, the tested meter along with the original test certificate has to be produced at site(premise) prior to effecting of service connection. Such applicants are eligible for exemption of monthly meter rent.
-
- Form Submission:
-
After submitting the application online, the applicant shall take a print out of the system generated form, and hand over to the KSEB Ltd personnel, after affixing signature & photograph along with other required documents, during site inspection / while effecting service connection. In the case of new Contract Demand Based billing connections, Service Connection Agreement in non-judicial stamp paper has to be executed.Please produce the original document for verification. - KSEBL will be forced to terminate the service connection and dismantle service connection without prior notice, if it is proved at any stage that the service connection was availed by hiding facts/fabricating false consents or orders. Any amount remitted by such consumer is liable to be forfeited. The consumer will be liable for any loss sustained by KSEBL on this account.
-